NEW QUESTION 33
In a manufacturing plant, two purchase components P1 and P2 and a resource R1 are required to assemble a product. The cost of the assembly is calculated by using thestandard costing method. The work definition and resource rates of the assembly have been defined as required.
A cost accountant is estimating cost of the assembly, analyzing rolled-up costs before finally publishing estimates as frozen standards to cost accounting by using a cost planning scenario. While reviewing rolled up costs, the extended costs of purchase components are not included in a rolled-up scenario.
Identify the reason.

  • A. Create Accounting Distributions was not initiated.
  • B. Costs for purchase components P1and P2 are not defined in cost accounting.
  • C. Purchase components P1 and P2 are not associated with Material cost plan of the cost planning scenario.
  • D. Create Accounting was not initiated.

Answer: A

 

NEW QUESTION 34
During a Manufacturing Cloud implementation, the Production Supervisor wants to close thework orders for last month and wants to make sure that the work orders include the correct cost.
Identify the approach to be taken by the Production Supervisor.

  • A. The Production Supervisor needs to include all costs and variances in last month's work orders and close them; however, the work orders where updates are expected, should not be closed.
  • B. The Production Supervisor need not include cost variances while costing last month's workorders because those can be applied directly in subledger accounting.
  • C. The Production Supervisor should make sure that all costs are included while closing last month's work orders; however, variances can be included after closing the work orders.
  • D. Work order costs can be updated anytime regardless of the status of the work order.

Answer: A

 

NEW QUESTION 35
Which two steps should you use to create a new Oracle Transactional Business Intelligence report in the ManufacturingCloud?

  • A. Use the Manufacturing subject area to select the report columns and create the report.
  • B. Use ibots to create the report.
  • C. Use Business Intelligence answers to create the report.
  • D. Use Business Intelligence publisher to create a template anduse that template to create the report.

Answer: C,D

Explanation:
Explanation
You can use Oracle Transactional Business Intelligence to create analysis and Oracle Business Intelligence Publisher to create reports.

 

NEW QUESTION 36
A customer has a distribution warehouse (DW) for After Sales and Service and an in-house manufacturing plant (MP). Sales orders are created and shipped from DW.
Identify the two Sourcing Rules that need to be set for order promising to schedule the order.

  • A. Define Local sourcing rule for organization DW: Source Type Transfer From, Source MP
  • B. Define Local sourcing rule for organization MP: Source Type Make At, Source MP
  • C. Define Local sourcing rule for organization DW: Source Type Make From, Source MP
  • D. Define Local sourcing rule for organization MP: Source Type Transfer To, Source DW

Answer: A,B

 

NEW QUESTION 37
You arereviewing the production status of your manufacturing plant shop floor as a production supervisor.
Your production manager wants a report on a work order statuswhich is reserved against a particular customer.
The final assembly of the work order is serialized.
Which option shows the steps to complete the task using the mobile application?

  • A. Search the work order by customer name to open the work order details page> Click Actions and select the E-mail icon> Select required work orders> Select the e-mail client, enter the recipient's e-mail, andclick Send.
  • B. Use your mobile camera to scan the bar coded serial number of the final assembly> Upload the barcode to open the work order details page> Select required work orders> Click Social icon (OSN) > Select recipient, and click Share.
  • C. Select the infotile Customer to open the work order details page> Click Actions and select the E-mail icon> Select required work orders>Select the e-mail client, enter the recipient's e-mail, and click Send.
  • D. Use your mobile camera to scan the bar coded serial number of the final assembly> Upload the barcode to open the work order details page > Click Actions and select the E-mail icon> Select required work orders> Select the e-mail client, enter the recipient's e-mail, and click Send.

Answer: D

 

NEW QUESTION 38
Identify three requirements fulfilled by nonstandard work orders.

  • A. Repair
  • B. Rescheduling
  • C. Rework
  • D. Prototype

Answer: A,C,D

 

NEW QUESTION 39
To reduce the subassembly stock with no impact on material planning of child components of the subassemblies stock, you need to modify the multilevel item structure of a product.
Identify the action that meets this requirement.

  • A. Change the Supply Type = Phantom in Item definition and Work Definition, for subassemblies having high inventory stock.
  • B. Change the Supply Type = Operation Pull in Item definition and Work Definition, for subassemblies having high inventory stock.
  • C. Change the Supply Type = Assembly Pull in Item definition and Work Definition, for subassemblies having high inventory stock.
  • D. Change the Supply Type = Push in Itemdefinition and Work Definition, for subassemblies having high inventory stock.

Answer: C

 

NEW QUESTION 40
The Manufacturing Engineer, responsible for creating and maintaining the Work Definitions, hasscheduled the Process Item Structure Changes to Work Definitions program. However, after the execution of the program the engineer did not receive a notification with the details of the Item Structure changes.
Which two reasons could cause this?

  • A. The engineer does not have Data access to Items.
  • B. The engineer does not have Dataaccess to Item Structures.
  • C. The engineer does not have Data access to Items Attributes.
  • D. The engineer does not have the Manage Work Definitions function privilege.
  • E. The engineer does not have Data access to Manufacturing plant in which the Item Structure change was performed.

Answer: D,E

 

NEW QUESTION 41
Identify the three sources from which supply chain orchestration (SCO) can create the work orders.

  • A. Planning
  • B. Order Management
  • C. Procurement
  • D. Quality
  • E. Inventory Min-Max Planning

Answer: A,B,C

 

NEW QUESTION 42
Your customer is a light assembly manufacturing company that doesn't require shop floor control. A manufacturing engineer wants to generate a work definition automatically for some items, and wants to eliminate the explicit maintenance of work definitions.
Which three steps must be completed and verified in the Work Definition area?

  • A. Select a standard operation that is to be used in automatic work definition by enabling the attribute Default for automatic work definition.
  • B. Select a resource that is to be used inautomatic work definition by enabling the attribute Default for automatic work definition.
  • C. Ensure the predefined work definition name ORA_MAIN name is active.
  • D. Ensure the item isa standard item with a secondary item structure.
  • E. Ensure there is only one default standard operation at a given point in time.

Answer: A,C,D

 

NEW QUESTION 43
Identify the three changes that are allowed to be made to active Work Definition in a Work Center, without creating a new version.

  • A. Delete an Operation
  • B. Completion Subinventory
  • C. Production Priority
  • D. Costing Priority
  • E. Add an Operation

Answer: B,C,E

 

NEW QUESTION 44
TheManufacturing plant has two 8-hour shifts for the work center WC1: Day Shift and Night Shift. You associate four units each for resources R1, R2, R3, and R4 to the work center WC1. The customer wants to assign all units of resource R2 available for Day andNight Shift.
Identify the correct sequence of steps to achieve this requirement.

  • A. Associate Resource R2 with Work Center WC1> Deselect the Available 24 Hours check box> Resource Availability region> Enter 4 in Day Shift Column> Enter 4 in Night Shift Column.
  • B. Associate Resource R2 with Work Center WC1> Deselect the Available 24 Hours check box> Resource Availability region> Enter 2 in Day Shift Column> Enter 2 in Night Shift Column
  • C. Associate Resource R2 with Work Center WC1> Select the Available 24 Hours check box> Resource Availability region> Enter 2 in Day Shift Column > Enter 2 in Night Shift Column.
  • D. Associate Resource R2 with Work Center WC1> Select Available 24 Hours check box> Resource Availability region> Enter 4 in Day Shift Column> Enter 4 in Night Shift Column.

Answer: C

 

NEW QUESTION 45
A Production operator in your company is required to report production activities, suchas completing or scrapping production units, by referencing a work definition without creating work orders.
Identify the manufacturing transaction that a production operator can perform for reporting such activities.

  • A. Operation Transactions
  • B. Movement request
  • C. Orderless Transactions
  • D. Resource Transactions
  • E. Material Transactions

Answer: C

 

NEW QUESTION 46
A manufacturing cloud user wants to print information available in the work order in PDF.
Identify the three reports that the user can print directly from the work order screen using the Print PDF action.

  • A. Print Component List
  • B. Resource List
  • C. Print Labels
  • D. Bill of material
  • E. Work Order Traveler

Answer: A,C,E

 

NEW QUESTION 47
Identify the two configurations in Supply Chain cloud applications of Product Information Management (PIM) and Order promising (GOP), which must be set to process the Back-to-Back order with Make Supply Order, for a nonstocked item.

  • A. Set a local sourcing rule in GOP to determine supply creation option as Make.
  • B. Set the nonstocked item to be back-to-back enabled in Product Information Management (PIM).
  • C. Create Supply Order Orchestration Defaulting and Enrichment Rule for the nonstocked item.
  • D. Create Supply Chain Orchestration Supply Execution Document Creation Rule for the nonstocked item.
  • E. Set the global sourcing rule in GOP to determine supply creation option as Make.

Answer: B,E

 

NEW QUESTION 48
A Manufacturing Engineer in a plant is creating an alternative manufacturing process for an item using its existing Work Definitions. After copying from the existing Work DefinitionWD1 to the alternative Work Definition WD2, the engineer finds that the operation items were not copied in the alternative manufacturing process WD2.
Identify the reason.

  • A. The Item and Structure Name were changed in the new Work Definition WD2 during creation.
  • B. The StartData was not populated in the new Work Definition WD2 during creation.
  • C. The Production Priority was not populated in the new Work Definition WD2 duringcreation.
  • D. The Item and Structure Name in the existing Work Definition WD1 were retained in the new Work Definition WD2 as well during creation.

Answer: B

 